Analisa Jarak Paralel Antara Konduktor Sistem Grounding Grid PLTP Lahendong Unit 5 Dan 6
DOI:
https://doi.org/10.35793/jtek.v7i3.20770Abstract
Abstract— To be able to secure and safety the equipment and the workers who work in the power plant area PLTP Lahendong with power capasity 2 x 20 MW, of course, required the earthing system design quality, reliable and efficient whereby the grounding grid resistance, voltage step and touch voltage according to the calculations contained in IEEE Std 80 -2000. This research will discuss the evaluation of system design with respect to the value of earthing resistance grounding grid, mesh voltage and step voltage. Evaluation parameters - parameters according to calculations published in IEEE Std 80-2000. Results from this study system grounding of PLTP Lahendong unit 5 and 6 well the categorized and meet the standart.
Keywords: Resistance grounding, step voltage, spacing between parallel conductors, touch voltage,.
Abstrak— Sistem pentanahan yang berkualitas, handal dan efisien adalah merupakan persyaratan utama dalam merancang suatu sistem pentahanan untuk dapat mengamankan peralatan dan para pekerja di area pembangkit. Penelitian ini bertujuan untuk menganalisis desain Grid Pentanahan PLTP Lahendong Unit 5 dan 6 dengan kapasitas daya 2x20 MW berdasarkan metode IEEE Std 80-2000. Analisis dilakukan terhadap beberapa parameter berupa luas penampang konduktor, nilai tahanan grid pentanahan tegangan sentuh dan tegangan langkah. Hasil dari penelitian menunjukkan bahwa sistem pentanahan pada PLTP Lahendong Unit 5 dan 6 dikategorikan baik dan memenuhi standar.
Kata Kunci : Jarak paralel antara konduktor, Tahanan tanah, Tegangan langkah, Tegangan sentuh.Â
References
A. Arismunandar, DR. M. A. Sc, 1997, Teknik Tenaga Listrik, Pradnya Paramita, Jakarta
G Turan. 1986. Electrical Power Distibution System Engineering. New York : McGraw-Hill Book Company
Grigsby, Leonard L. 2006. Electrical Power Engineering Handbook – Power System Stability and Control. Boca Raton : Taylor & Francis Group, LLC
IEEE 80-2000, IEEE Guide for safety in C Subtation Grounding. American National Standart Institute. IEEE Power Engineering Society 2000.
SNI PUIL 2000. Amandemen 1 Persyarata Umum Instalasi Listrik (PUIL). Badan Standarisasi Nasional 2000
Suryatmo .F, 1990, Teknik Listrik Instalasi Gaya, Tarsito, Bandung
TS Hutauruk. Ir. Msc, 1999, Pengetahanan Netral Sistem Tenaga, Erlangga, Jakarta.
Downloads
Published
Issue
Section
License
Jurnal Teknik Elektro dan Komputer is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.